Article
Publication date: 26 December 2023

Farshad Peiman, Mohammad Khalilzadeh, Nasser Shahsavari-Pour and Mehdi Ravanshadnia

Earned value management (EVM)–based models for estimating project actual duration (AD) and cost at completion using various methods are continuously developed to improve the…

Abstract

Purpose

Earned value management (EVM)–based models for estimating project actual duration (AD) and cost at completion using various methods are continuously developed to improve the accuracy and actualization of predicted values. This study primarily aimed to examine natural gradient boosting (NGBoost-2020) with the classification and regression trees (CART) base model (base learner). To the best of the authors' knowledge, this concept has never been applied to EVM AD forecasting problem. Consequently, the authors compared this method to the single K-nearest neighbor (KNN) method, the ensemble method of extreme gradient boosting (XGBoost-2016) with the CART base model and the optimal equation of EVM, the earned schedule (ES) equation with the performance factor equal to 1 (ES1). The paper also sought to determine the extent to which the World Bank's two legal factors affect countries and how the two legal causes of delay (related to institutional flaws) influence AD prediction models.

Design/methodology/approach

In this paper, data from 30 construction projects of various building types in Iran, Pakistan, India, Turkey, Malaysia and Nigeria (due to the high number of delayed projects and the detrimental effects of these delays in these countries) were used to develop three models. The target variable of the models was a dimensionless output, the ratio of estimated duration to completion (ETC(t)) to planned duration (PD). Furthermore, 426 tracking periods were used to build the three models, with 353 samples and 23 projects in the training set, 73 patterns (17% of the total) and six projects (21% of the total) in the testing set. Furthermore, 17 dimensionless input variables were used, including ten variables based on the main variables and performance indices of EVM and several other variables detailed in the study. The three models were subsequently created using Python and several GitHub-hosted codes.

Findings

For the testing set of the optimal model (NGBoost), the better percentage mean (better%) of the prediction error (based on projects with a lower error percentage) of the NGBoost compared to two KNN and ES1 single models, as well as the total mean absolute percentage error (MAPE) and mean lags (MeLa) (indicating model stability) were 100, 83.33, 5.62 and 3.17%, respectively. Notably, the total MAPE and MeLa for the NGBoost model testing set, which had ten EVM-based input variables, were 6.74 and 5.20%, respectively. The ensemble artificial intelligence (AI) models exhibited a much lower MAPE than ES1. Additionally, ES1 was less stable in prediction than NGBoost. The possibility of excessive and unusual MAPE and MeLa values occurred only in the two single models. However, on some data sets, ES1 outperformed AI models. NGBoost also outperformed other models, especially single models for most developing countries, and was more accurate than previously presented optimized models. In addition, sensitivity analysis was conducted on the NGBoost predicted outputs of 30 projects using the SHapley Additive exPlanations (SHAP) method. All variables demonstrated an effect on ETC(t)/PD. The results revealed that the most influential input variables in order of importance were actual time (AT) to PD, regulatory quality (RQ), earned duration (ED) to PD, schedule cost index (SCI), planned complete percentage, rule of law (RL), actual complete percentage (ACP) and ETC(t) of the ES optimal equation to PD. The probabilistic hybrid model was selected based on the outputs predicted by the NGBoost and XGBoost models and the MAPE values from three AI models. The 95% prediction interval of the NGBoost–XGBoost model revealed that 96.10 and 98.60% of the actual output values of the testing and training sets are within this interval, respectively.

Research limitations/implications

Due to the use of projects performed in different countries, it was not possible to distribute the questionnaire to the managers and stakeholders of 30 projects in six developing countries. Due to the low number of EVM-based projects in various references, it was unfeasible to utilize other types of projects. Future prospects include evaluating the accuracy and stability of NGBoost for timely and non-fluctuating projects (mostly in developed countries), considering a greater number of legal/institutional variables as input, using legal/institutional/internal/inflation inputs for complex projects with extremely high uncertainty (such as bridge and road construction) and integrating these inputs and NGBoost with new technologies (such as blockchain, radio frequency identification (RFID) systems, building information modeling (BIM) and Internet of things (IoT)).

Practical implications

The legal/intuitive recommendations made to governments are strict control of prices, adequate supervision, removal of additional rules, removal of unfair regulations, clarification of the future trend of a law change, strict monitoring of property rights, simplification of the processes for obtaining permits and elimination of unnecessary changes particularly in developing countries and at the onset of irregular projects with limited information and numerous uncertainties. Furthermore, the managers and stakeholders of this group of projects were informed of the significance of seven construction variables (institutional/legal external risks, internal factors and inflation) at an early stage, using time series (dynamic) models to predict AD, accurate calculation of progress percentage variables, the effectiveness of building type in non-residential projects, regular updating inflation during implementation, effectiveness of employer type in the early stage of public projects in addition to the late stage of private projects, and allocating reserve duration (buffer) in order to respond to institutional/legal risks.

Originality/value

Ensemble methods were optimized in 70% of references. To the authors' knowledge, NGBoost from the set of ensemble methods was not used to estimate construction project duration and delays. NGBoost is an effective method for considering uncertainties in irregular projects and is often implemented in developing countries. Furthermore, AD estimation models do fail to incorporate RQ and RL from the World Bank's worldwide governance indicators (WGI) as risk-based inputs. In addition, the various WGI, EVM and inflation variables are not combined with substantial degrees of delay institutional risks as inputs. Consequently, due to the existence of critical and complex risks in different countries, it is vital to consider legal and institutional factors. This is especially recommended if an in-depth, accurate and reality-based method like SHAP is used for analysis.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 6 June 2020

Reza Fattahi, Reza Tavakkoli-Moghaddam, Mohammad Khalilzadeh, Nasser Shahsavari-Pour and Roya Soltani

Risk assessment is a very important step toward managing risks in various organizations and industries. One of the most extensively applied risk assessment techniques is failure…

Abstract

Purpose

Risk assessment is a very important step toward managing risks in various organizations and industries. One of the most extensively applied risk assessment techniques is failure mode and effects analysis (FMEA). In this paper, a novel fuzzy multiple-criteria decision-making (MCDM)-based FMEA model is proposed for assessing the risks of different failure modes more accurately.

Design/methodology/approach

In this model, the weight of each failure mode is considered instead of risk priority number (RPN). Additionally, three criteria of time, cost and profit are added to the three previous risk factors of occurrence (O), severity (S) and detection (D). Furthermore, the weights of the mentioned criteria and the priority weights of the decision-makers calculated by modified fuzzy AHP and fuzzy weighted MULTIMOORA methods, respectively, are considered in the proposed model. A new ranking method of fuzzy numbers is also utilized in both proposed fuzzy MCDM methods.

Findings

To show the capability and usefulness of the suggested fuzzy MCDM-based FMEA model, Kerman Steel Industries Factory is considered as a case study. Moreover, a sensitivity analysis is conducted for validating the achieved results. Findings indicate that the proposed model is a beneficial and applicable tool for risk assessment.

Originality/value

To the best of authors’ knowledge, no research has considered the weights of failure modes, the weights of risk factors and the priority weights of decision-makers simultaneously in the FMEA method.

Details

Journal of Enterprise Information Management, vol. 33 no. 5
Type: Research Article
ISSN: 1741-0398

Keywords

Article
Publication date: 21 February 2020

Farhad Hosseinzadeh, Behzad Paryzad, Nasser Shahsavari Pour and Esmaeil Najafi

The optimization and tradeoff of cost-time-quality-risk in one dimension and this four-dimensional problem in ambiguous mode and risk can be neither predicted nor estimated. This…

Abstract

Purpose

The optimization and tradeoff of cost-time-quality-risk in one dimension and this four-dimensional problem in ambiguous mode and risk can be neither predicted nor estimated. This study aims to solve this problem and rank fuzzy numbers using an innovative algorithm “STHD” and a special technique “radius of gyration” (ROG) for fuzzy answers, respectively.

Design/methodology/approach

First, it is the optimization of a fully fuzzy four-dimensional problem which has never been dealt with in regard to risk in ambiguous mode and complexities. Therefore, the risk is a parameter which has been examined neither in probability and estimableness mode nor in the ambiguous mode so far. Second, it is a fully fuzzy tradeoff which, based on the principle of incompatibility “Zadeh, 1973”, proposes that when the complexity of a system surpasses the limited point, it becomes impossible to define the performance of that system accurately, precisely and meaningfully. The authors believe that this principle is the source of fuzzy logic. Third, for calculating and ranking fuzzy numbers of answers, a special technique for fuzzy numbers has been used. Fourth, For the sake of ease, precision and efficiency, an innovative algorithm called the technique of hunting dolphins “STHD” has been used. Finally, the problem is very close to reality. By applying risk in ambiguous mode, the problem has been realistically looked at.

Findings

The results showed that the algorithm was highly robust, with its performance depending very little on the regulation of the parameters. Ranking fuzzy numbers using the ROG indicated the flexibility of fuzzy logic, and it was also determined that the most appropriate regulations were to ensure low time, risk and cost but maximum quality in calculations, which were produced non-uniformly based on the levels of Pareto answers.

Originality/value

The ROG and Chanas Fuzzy Critical Path Method as developed by other researchers have been used. Despite the increase in limitations, parameters can develop. The originality of this study with regard to evaluating the results of tradeoff combinatorial optimization is upon decision-making which has a special and highly strategic role in the fate of the project, with the research been conducted with a special approach and different tools in a fully fuzzy environment.