Article
Publication date: 20 February 2024

Huy Minh Vo, Jyh-Bin Yang and Veerakumar Rangasamy

Construction projects commonly encounter complicated delay problems. Over the past few decades, numerous delay analysis methods (DAMs) have been developed. There is no consensus…

Abstract

Purpose

Construction projects commonly encounter complicated delay problems. Over the past few decades, numerous delay analysis methods (DAMs) have been developed. There is no consensus on whether existing DAMs effectively resolve delays, particularly in the case of complex concurrent delays. Thus, the primary objective of this study is to undertake a comprehensive and systematic literature review on concurrent delays, aiming to answer the following research question: Do existing delay analysis techniques deal with concurrent delays well?

Design/methodology/approach

This study conducts a comprehensive review of concurrent delays by both bibliometric and systematic analysis of research publications published between 1982 and 2022 in the Web of Science (WoS) and Scopus databases. For quantitative analysis, a bibliometric mapping tool, the VOSviewer, was employed to analyze 68 selected publications to explore the co-occurrence of keywords, co-authorship and direct citation. Additionally, we conducted a qualitative analysis to answer the targeted research question, identify academic knowledge gaps and explore potential research directions for solving the theoretical and practical problems of concurrent delays.

Findings

Concurrent delays are a critical aspect of delay claims. Despite DAMs developed by a limited number of research teams to tackle issues like concurrence, float consumption and the critical path in concurrent delay resolution, practitioners continue to face significant challenges. This study has successfully identified knowledge gaps in defining, identifying, analyzing and allocating liability for concurrent delays while offering promising directions for further research. These findings reveal the incompleteness of available DAMs for solving concurrent delays.

Practical implications

The outcomes of this study are highly beneficial for practitioners and researchers. For practitioners, the discussions on the resolution process of concurrent delays in terms of identification, analysis and apportionment enable them to proactively address concurrent delays and lay the groundwork for preventing and resolving such issues in their construction projects. For researchers, five research directions, including advanced DAMs capable of solving concurrent delays, are proposed for reference.

Originality/value

Existing research on DAMs lacks comprehensive coverage of concurrent delays. Through a scientometric review, it is evident that current DAMs do not deal with concurrent delays well. This review identifies critical knowledge gaps and offers insights into potential directions for future research.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 18 February 2019

Yijun Zhou, Yu Yang and Jyh-Bin Yang

Effective BIM application hinges on the development of appropriate strategies for its implementation. Though some strategies have been deployed to facilitate BIM implementation in…

3110

Abstract

Purpose

Effective BIM application hinges on the development of appropriate strategies for its implementation. Though some strategies have been deployed to facilitate BIM implementation in China, their outcomes are not clear. The purpose of this paper is to provide recommendations regarding appropriate strategies for promoting the development and implementation of BIM in China based on lessons learned from advanced implementation experiences in other countries.

Design/methodology/approach

First, existing strategies are investigated and barriers to BIM implementation mentioned in previous studies are summarized. Then, the identified barriers are mapped to the strategy contents. Finally, a comparative analysis on different areas is conducted to propose suggestions for identified items of BIM implementation strategies that need to be improved.

Findings

Six unaddressed barriers to BIM implementation strategies in China were identified from the mapping results: insufficient government lead/direction, organizational issues, legal issues, high cost of application, resistance to change of thinking mode and insufficient external motivation.

Originality/value

The findings of this study can be used to facilitate the development of appropriate strategies within the public and private sectors for promoting BIM implementation in China and elsewhere.

Details

Engineering, Construction and Architectural Management, vol. 26 no. 3
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 16 June 2023

Jyh-Bin Yang and Tzu-Hua Lai

This study aims to review earned value management (EVM)-relative methods, including the original EVM, earned schedule method (ESM) and earned duration management (EDM(t)). This…

Abstract

Purpose

This study aims to review earned value management (EVM)-relative methods, including the original EVM, earned schedule method (ESM) and earned duration management (EDM(t)). This study then proposes a general implementation procedure and some basic principles for the selection of EVM-relative methods.

Design/methodology/approach

After completing an intensive literature review, this study conducts a case study to examine the forecasting performance of project duration using the EVM, ESM and EDM(t) methods.

Findings

When the project is expected to finish on time, ESM with a performance factor equal to 1 is the recommended method. EDM(t) would be the most reliable method during a project's entire lifetime if EDM(t) is expected to be delayed based on past experience.

Research limitations/implications

As this research conducts a case study with only one building construction project, the results might not hold true for all types of construction projects.

Practical implications

EVM, ESM and EDM(t) are simple and data-accessible methods. With the help of a general implementation procedure, applying all three methods would be better. The power of the three methods is definitely larger than that of choosing only one for complex construction projects.

Originality/value

Previous studies have discussed the advantages and disadvantages of EVM, ESM and EDM(t). This study amends the available outcomes. Thus, for schedulers or researchers interested in implementing EVM, ESM and EDM(t), this study can provide more constructive instructions.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 20 October 2023

Jyh-Bin Yang and Ying-Fu Chen

An S-curve is an essential project-management tool. However, it is difficult to adjust S-curve to deal with a force majeure event. The present study develops four valuable…

Abstract

Purpose

An S-curve is an essential project-management tool. However, it is difficult to adjust S-curve to deal with a force majeure event. The present study develops four valuable adjustment approaches, designed to achieve a compromise between the views of the client and contractor. These can be used to control projects after a force majeure event.

Design/methodology/approach

The present study develops four adjustment approaches, which can be used to achieve a compromise between the views of the client and those of the contractor when controlling projects after a force majeure. To determine the S-curves during a force majeure event, two approaches can be selected: BCWS (budgeted cost of scheduled work)-base approach, or BCWP (budgeted cost of work performed)-base approach. To determine the rest of S-curves after a force majeure event, two approaches can be considered: maintaining the original curve of the remaining BCWS, or allocating the original curve of the remaining BCWS. Based on the validation of three empirical cases, drawn from a professional project-management website, this study confirms the feasibility of four proposed empirical approaches and a selection procedure for S-curve adjustment.

Findings

The S-curve-adjustment approaches presented here can be used to deal with cases that are ahead of, on and behind schedule. Using the proposed approaches and selection procedure, contractors can easily revise S-curves and control projects more effectively. To deal with a force majeure event, such as COVID-19, they are strongly advised to adopt the approaches labeled SA-A1 (to adjust the S-curve based on the extension ratio multiplied by the difference in progress during the force majeure) and SA-B1 (to maintain the original curve of the remaining BCWS) for the A/E and E/F curves, respectively.

Research limitations/implications

The proposed approaches can be used in cases of continuous construction during force majeure events. If construction work is totally suspended during such an event, it will be necessary to fine-tune the proposed approaches.

Originality/value

Previous studies have used case-oriented or mathematical-simulation approaches to forecast S-curves. The present study proposes simple approaches that allow the client and contractor to adjust the S-curve easily after a force majeure event. These approaches can be used to adjust work and project-completion targets within an extended duration. Selecting the right S-curve adjustment approach can help to control the remainder of the project, reducing the possibility of delay claims.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 1 March 2004

J.B. Yang

This paper presents a hybrid artificial intelligence (AI) system capable of integrating techniques of case‐based reasoning, rule induction and expert system, using them for…

Abstract

This paper presents a hybrid artificial intelligence (AI) system capable of integrating techniques of case‐based reasoning, rule induction and expert system, using them for knowledge acquisition and problem solving of selecting appropriate retaining wall systems at the project planning stage. The proposed hybrid system can eliminate the bottleneck of knowledge acquisition in developing a knowledge‐based system and improve the solution quality of the AI‐based system. Test results indicate that solutions generated by the proposed hybrid system are better than those generated by using a single technique.

Details

Construction Innovation, vol. 4 no. 1
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 20 February 2017

Siqing Shan, Mengni Liu and Xiaobo Xu

With the development of mobile internet, instant messaging (IM) applications have gradually changed the way to receive information and communicate with friends. Considered as one…

1660

Abstract

Purpose

With the development of mobile internet, instant messaging (IM) applications have gradually changed the way to receive information and communicate with friends. Considered as one of the important social media platforms, WeChat is the most popular IM application in China. This paper aims to examine the influence factors of haze information’s dissemination in WeChat.

Design/methodology/approach

Based on the theory of information dissemination and the theory of motivation, three information dissemination elements including information source, information and information receiver were proposed in the structural equation model. The model was tested using data collected from both online and offline questionnaire survey results. The data analysis from 170 valid responses confirmed the path effects that emotional motivation, social motivation of information receiver and the credibility of information source positively influenced WeChat users’ re-transmission intention and information emotional tendency negatively influenced their re-transmission intention.

Findings

The research model revealed these key factors that affected dissemination of haze information in WeChat. More importantly, it provided a decision-making framework to release the public emergency information in WeChat. Hence, the paper made an important contribution to practical guidance to relevant decision makers.

Originality/value

This study contributes to the literature on examining factors affecting the haze information transmission in WeChat. A framework was proposed to describe the information dissemination process which comprises information source, information and information receiver.

1 – 6 of 6