1 – 10 of over 14000Maria Cleofe Giorgino and Federico Barnabè
Drawing motivation from the greater exposure to uncertainty and condition changes that affect large projects due to their long lifecycle, this paper aims to investigate how the…
Abstract
Purpose
Drawing motivation from the greater exposure to uncertainty and condition changes that affect large projects due to their long lifecycle, this paper aims to investigate how the time factor affects the use of governance mechanisms to pursue the success of these projects.
Design/methodology/approach
To pursue its aim, the article applies the dichotomization between the hard and soft mechanisms of project governance to the analysis of a historical case study, whose findings are organized over the short, medium and long periods. The case selected is referred to the peculiar water system, made up of tunnels named “bottini,” that was in use in Siena (Italy) as the old aqueduct. Specifically, the study focuses on the project of expansion of this water system that was realized during the 14th century for the construction of the “Bottino maestro di Fontegaia.”
Findings
This article highlights the different relevance that, during the lifecycle of large projects, is assumed by hard and soft governance mechanisms, with the former having main relevance in a short and medium period, and the latter usually emerging in the medium period and, subsequently, playing a growing role for the project success in the long period.
Originality/value
The article contributes to the literature on large projects by providing novel insights about how the time factor impacts the governance of these projects. Furthermore, the case study, with its unique history, highlights the relevance of combining effectively the hard and the soft dimensions of project governance to pursue success.
Details
Keywords
Saeed Akbari, Mostafa Khanzadi and Mohammad Reza Gholamian
To address requirements and specifications of construction project, academics need to build a project classification model. In recent years, project success concept, particularly…
Abstract
Purpose
To address requirements and specifications of construction project, academics need to build a project classification model. In recent years, project success concept, particularly on large-scale construction projects, has been a controversial issue, especially in developing countries. Hence, in this paper, after introducing a sustainable success index (SSI), a novel method called “rough set approach” had been adopted to induce decision rules and to classify construction projects. The paper aims to discuss these issues.
Design/methodology/approach
At first, 20 effective success factors and 15 success criteria based on three pillars of sustainability of economy, society and environment had been categorized. The research data used for analysis had been collected from 26 large-scale construction projects in Iran and five other countries. After collecting data collection, observations had been analyzed and 51 decision rules were generated, and the projects were classified. Eventually, in order to evaluate the performance of the generated rules, confusion matrix was applied, and the model was validated.
Findings
The results of the present study show that rough set theory (RST) can be an effective and valuable tool for building expert systems. Practical applications of these results along with limitations and future research are described.
Originality/value
Perhaps for the first time, in the present study, a number of large-scale construction projects are classified based on SSI. Applying RST for building rule-based system and classifying projects in construction project area are novel attempts undertaken in this paper. The rules induced in this study can be applied to develop a sustainable success prediction model in the future studies.
Details
Keywords
Anna Kadefors, Kirsi Aaltonen, Stefan Christoffer Gottlieb, Ole Jonny Klakegg, Pertti Lahdenperä, Nils O.E. Olsson, Lilly Rosander and Christian Thuesen
Relational contracting is increasingly being applied to complex and uncertain construction projects. However, it has proved hard to achieve stable performance and industry-level…
Abstract
Purpose
Relational contracting is increasingly being applied to complex and uncertain construction projects. However, it has proved hard to achieve stable performance and industry-level learning in this field. This paper employs an institutional perspective to analyze how legitimacy for relational contracting has been produced and challenged in Denmark, Finland, Norway and Sweden, including implications for dissemination and learning.
Design/methodology/approach
A collaborative case study design is used, where longitudinal accounts of the developments in relational contracting over more than 25 years in four Nordic countries were developed by scholars based in each country. The descriptions are underpinned by literature sources from research, practice and policy.
Findings
The countries share similar problem perceptions that have triggered the de-institutionalization of traditional contracting practices. Models and policies developed elsewhere are important sources of knowledge and legitimacy. Most countries have seen pendulum movements, where dissemination of relational contracting is followed by backlashes when projects fail to meet projected outcomes. Before long, however, relational contracting tends to re-emerge under new labels and in slightly new forms. Such a proliferation of concepts presents further obstacles to learning. Successful institutionalization is found to rely on realistic goals in combination with broad competence development at the organizational and industry levels.
Practical implications
In seeking inspiration from other countries, policymakers should go beyond contract models to also consider strategies to manage industry-level learning.
Originality/value
The paper provides a unique longitudinal cross-country perspective on the field of relational contracting. As such, it contributes to the small stream of literature on long-term institutional change in the construction sector.
Details
Keywords
Gro Holst Volden and Bjorn Andersen
The purpose of this paper is to study public project governance frameworks in various ministries and agencies in Norway, following the introduction of such a framework on the…
Abstract
Purpose
The purpose of this paper is to study public project governance frameworks in various ministries and agencies in Norway, following the introduction of such a framework on the topmost level (i.e. the cabinet) which applies to the very largest projects.
Design/methodology/approach
The study is methodologically designed as a qualitative assessment of project governance frameworks that apply to state-funded investment projects in selected sectors, based on data gathered through document reviews and interviews.
Findings
The study finds that all of the agencies have introduced their own project governance frameworks, which are basically consistent with the recommendations from the project management literature and with the cabinet’s overall requirements in Norway. By contrast, only one ministry has taken a formalized role as a project owner. Governance tasks thus seem to be extensively delegated to the subordinate agencies. This even includes strategic tasks such as project selection and portfolio management, and implies there is a risk that public project governance has a narrow and internal focus.
Originality/value
The paper is a first step toward a better understanding of public project governance as a hierarchical system and the relationship between project owners on three levels, the cabinet, the sectoral ministry, and the government agency.
Details
Keywords
Fredrik Brunes, Cecilia Hermansson, Han-Suck Song and Mats Wilhelmsson
This paper aims to analyze how nearby property prices are affected by new construction projects in Stockholm. If there is an impact on property prices, the authors endeavor to…
Abstract
Purpose
This paper aims to analyze how nearby property prices are affected by new construction projects in Stockholm. If there is an impact on property prices, the authors endeavor to investigate whether the effects vary among different areas within the municipality, for different groups of inhabitants and for different types of housing (i.e. public versus private housing).
Design/methodology/approach
The authors use a difference-in-difference specification in a hedonic model, and the sample consists of more than 90,000 observations over the period 2005-2013.
Findings
The results are robust and indicate that house prices in nearby areas increase following the completion of infill development. The results also indicate that infill development has a positive spillover effect on nearby dwelling prices only in areas with lower incomes, more public housing units and more inhabitants born abroad.
Originality/value
It provides an analysis on how nearby property prices are affected by new construction projects by creating a restricted control area, so as to make the treatment group and the control group more homogeneous. Thus, it mitigates any potential problems with spatial dependency, which can cause biased standard errors.
Details
Keywords
The purpose of this study is to investigate how procurement strategies may be designed to facilitate exploration and exploitation in construction projects.
Abstract
Purpose
The purpose of this study is to investigate how procurement strategies may be designed to facilitate exploration and exploitation in construction projects.
Design/methodology/approach
This paper is based on a literature review of organizational research and construction management literature together with a brief interview study of Swedish clients and contractors.
Findings
The theoretical and empirical findings propose that small and simple projects with low uncertainty and scarce resources may focus on exploitation to enhance short-term efficiency through traditional procurement strategies including delivery systems that separate the actors and their activities (i.e. pure design-build- or design-bid-build-contracts), fixed price payment and price focus in bid evaluation. Large complex projects with high uncertainty and customization benefit from combining exploration and exploitation to enhance sustainable performance. This requires collaborative procurement strategies including joint specification through early contractor involvement, cost reimbursement coupled with incentive-based payment, bid evaluation based on multiple criteria and collaborative tools and activities in partnering arrangements.
Research limitations/implications
This paper contributes to organizational learning literature by pinpointing the need for integrating procurement strategies that enhance combination of exploration and exploitation. The main contribution to the construction management literature involves the investigation of how procurement strategies may affect exploration and exploitation, as identified and articulated in the propositions developed in this paper.
Practical implications
From a practical perspective, the findings highlight the importance of tailoring procurement strategies to project characteristics to enhance a suitable balance between exploration and exploitation in construction projects.
Originality/value
The explicit focus on the operational project-level is uncommon but relevant in organizational learning literature.
Details
Keywords
Gavin Dennehy, Bobby Kennedy and John Spillane
The purpose of this study is to identify the factors relating to the integration and compliance of Building Control (Amendment) Regulations 2014 (BC(A)R 2014) in large Irish…
Abstract
Purpose
The purpose of this study is to identify the factors relating to the integration and compliance of Building Control (Amendment) Regulations 2014 (BC(A)R 2014) in large Irish construction organisations.
Design/methodology/approach
To achieve the aim, a mixed method approach is adopted, initially, providing a critique of the literature review, followed by a combination of 7 semi-structured interviews and 30 questionnaires from industry practitioners.
Findings
Findings demonstrate that BC(A)R has had a significant positive effect on the industry, eliminating previous bad practice, by increasing the accountability for professionals signing-off on new buildings, and highlights the emphasis on certification in successfully achieving practical completion on projects.
Practical implications
The findings provide further justification on the need for compliance, and integration, of BC(A)R in the Irish construction sector, offering further evidence, where needed, on the benefit of its adoption.
Originality/value
The originality and value of this research lies in the limited number of studies in the area, particularly in the context of large Irish construction projects, which this study aims to fulfil.
Details
Keywords
Rolf Barlindhaug and Berit Irene Nordahl
This paper aims to investigate whether developers’ ask lower prices on homes in redevelopment sites than they do on similar units in smaller developments completed over a shorter…
Abstract
Purpose
This paper aims to investigate whether developers’ ask lower prices on homes in redevelopment sites than they do on similar units in smaller developments completed over a shorter time span. It also investigates whether developers price units differently at different stages of the redevelopment process. The development of designated redevelopment areas often consists of multiple projects spread across several years, some in parallel, some sequential. New units are put on the market in a piecemeal fashion, and infrastructure, shared green spaces and shared facilities are installed successively.
Design/methodology/approach
A hedonic price model is used to analyse sales prices of 7,000 new apartments in Oslo sold between 2011 and 2015, all else being equal. The paper distinguishes between infill as one-stage projects, and multi-staged competitive and multi-staged monopolistic redevelopments.
Findings
Dwellings in redevelopment projects sell at a lower price than similar dwellings in infill projects. In competitive redevelopments, those in charge of the last projects put a slightly higher price on apartments. In redevelopments involving only one developer, the last stages ask the lowest prices.
Research limitations/implications
This research expands our understanding of developers’ pricing behaviour. Developers supplying housing for the private market through redevelopments land are willing to take risks particularly in the initial stage.
Practical implications
The findings indicate that credit institutions financing developers’ projects need to take into account the structure of selling prices, including lower prices and higher risk of pursuing redevelopment projects.
Social implications
Gaining a better understanding of developers’ pricing behaviour deepens our insights into the dynamics of market-led urban brownfield developments; this knowledge may moreover inform policies on sustainable urban growth.
Originality/value
An original investigation of housing transactions in urban brownfield sites in Oslo provides fresh insights into developers’ pricing behaviour.
Details
Keywords
Rouzbeh Shabani, Tobias Onshuus Malvik, Agnar Johansen and Olav Torp
Uncertainty management (UM) in projects has been a point of attention for researchers for many years. Research on UM has mainly been aimed at uncertainty analyses in the front-end…
Abstract
Purpose
Uncertainty management (UM) in projects has been a point of attention for researchers for many years. Research on UM has mainly been aimed at uncertainty analyses in the front-end and managing uncertainty in the construction phase. In contrast, UM components in the design phase have received less attention. This research aims to improve knowledge about the key components of UM in the design phase of large road projects.
Design/methodology/approach
This study adopted a literature review and case study. The literature review was used to identify relevant criteria for UM. These criteria helped to design the interview guide. Multiple case study research was conducted, and data were collected through document study and interviews with project stakeholders in two road projects. Each case's owners, contractors and consultants were interviewed individually.
Findings
The data analysis obtained helpful information on the involved parties, process and exploit tools and techniques during the design phase. Johansen's (2015) framework [(a) human and organisation, (b) process and (c) tools and techniques)] was completed and developed by identifying relevant criteria (such as risk averse or risk-taker, culture and documentation level) for each component. These criteria help to measure UM performance. The authors found that owners and contractors are major formal UM actors, not consultants. Empirical data showed the effectiveness of Web-based tools in UM.
Research limitations/implications
The studied cases were Norwegian, and this study focussed on uncertainties in the project's design phase. Relevant criteria did not cover all the criteria for evaluating the performance of UM. Qualitative evaluation of criteria allows further quantitative analysis in the future.
Practical implications
This paper gave project owners and managers a better understanding of relevant criteria for measuring UM in the owners and managers' projects. The paper provides policy-makers with a deeper understanding of creating rigorous project criteria for UM during the design phase. This paper also provides a guideline for UM in road projects.
Originality/value
This research gives a holistic evaluation of UM by noticing relevant criteria and criteria's interconnection in the design phase.
Details
Keywords
Adriano Rehder, João Valsecchi Souza, Roberto Marx and Mario Sergio Salerno
Agile methods are increasingly being applied in the contexts of innovation beyond traditional information technology (IT) and physical product development projects, such as when…
Abstract
Purpose
Agile methods are increasingly being applied in the contexts of innovation beyond traditional information technology (IT) and physical product development projects, such as when process improvements are being implemented. Nevertheless, this phenomenon is still recent and little addressed in the literature, with few descriptions of empirical cases. This study aims to address this gap.
Design/methodology/approach
This multiple case study aims to present and discuss the application of Agile practices embedded in large companies’ innovation value chains, focusing on improvements of business processes. The following research question is pursued: How are large companies applying elements of Agile methods to their innovation processes when implementing incremental improvements in their operational processes? Based on the idea that the Agile-Stage-Gate model is an alternative to this challenge, this study investigates the application of this hybrid model in two large Brazilian companies by presenting their idiosyncrasies, lessons learned, adaptations, challenges and benefits.
Findings
Overall, it was observed that the experience with the application of the Agile-Stage-Gate model is positive for these companies, with better customer engagement, easier project control and increased productivity of the project team.
Originality/value
For those aiming to implement the Agile-Stage-Gate model, this paper identifies the main adaptations made in order to combine the purist approaches and critical success factors for its implementation.