Search results

1 – 10 of over 1000
Article
Publication date: 25 August 2022

Muhammad Waseem, Shahid Iqbal and Khalid Khan

The purpose of this study is to determine how project governance influences project success. According to the authors, such an effect is mediated by organizational support and…

Abstract

Purpose

The purpose of this study is to determine how project governance influences project success. According to the authors, such an effect is mediated by organizational support and project team cohesion. The direct and indirect effects of organizational support and project team cohesion provided helpful information. The authors’ objective is to contribute to the project management knowledge of how project team cohesion plays a significant role in project success.

Design/methodology/approach

Data were collected from 350 employees working in Pakistan’s oil and gas industry. Four prime oil and gas exploration companies were selected as samples based on their contribution to the revenue. SPSS v23 and AMOS v23 were used for constructing structural equation modeling and path analysis to examine the direct and indirect effects.

Findings

The results revealed that project governance is positively related to project success. Furthermore, organizational support and project team cohesion mediated the relationship between project governance and project success.

Originality/value

Team cohesion has been primarily a topic of interest in sports psychology literature, education and medical sciences. There is an expressed need to investigate team cohesion issues in the broad domain of organizational development, specifically the project management literature. This study contributed by discussing team cohesion in the project context. Second, project governance was investigated using the conservation of resources theory. The lens of intellectual capital was applied to examine intangible resources of project governance like rules, regulations and directives for project success.

Details

Journal of Facilities Management , vol. 22 no. 3
Type: Research Article
ISSN: 1472-5967

Keywords

Open Access
Article
Publication date: 28 June 2022

Sahar Jawad, Ann Ledwith and Rashid Khan

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and…

1755

Abstract

Purpose

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and successfully achieving project objectives has yet to be explored. This research investigates the enablers and barriers that influence the elements of PCS success and drive project objectives.

Design/methodology/approach

This study adopts a mixed approach of descriptive analysis and regression models to explore the impact of six PCS elements on project outcomes. Petroleum and chemical projects in Saudi Arabia were selected as a case study to validate the research model.

Findings

Data from a survey of 400 project managers in Saudi’s petroleum and chemical industry reveal that successful PCS are the key to achieving all project outcomes, but they are particularly critical for meeting project cost objectives. Project Governance was identified as the most important of the six PCS elements for meeting project objectives. A lack of standard processes emerged as the most significant barrier to achieving effective project governance, while having skilled and experienced project team members was the most significant enabler for implementing earned value.

Practical implications

The study offers a direction for implementing and developing PCS as a strategic tool and focuses on the PCS elements that can improve project outcomes.

Originality/value

This research contributes to project management knowledge and differs from previous attempts in two ways. Firstly, it investigates the elements of PCS that are critical to achieving project scope, schedule and cost objectives; secondly, enablers and barriers of PCS success are examined to see how they influence each element independently.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 29 May 2024

Gro Holst Volden, Morten Welde, Atle Engebø and Bjørn Sørskot Andersen

In the project initiation phase, an appraisal is needed to clarify the strategic problem and alternative solutions. Full-scale construction projects and simple solutions …

Abstract

Purpose

In the project initiation phase, an appraisal is needed to clarify the strategic problem and alternative solutions. Full-scale construction projects and simple solutions (do-minimum alternatives) should be assessed. The do-nothing alternative is the baseline for the appraisal and an option in itself. The paper explores the role of do-nothing and do-minimum alternatives in public project appraisal, which may significantly impact the attractiveness of a construction project.

Design/methodology/approach

The paper presents an empirical study from Norway, which requires external quality assurance (QA) of early project appraisals. The data include an extensive document review of 112 projects and interviews with 41 experts involved in the appraisal processes.

Findings

Of 112 appraisals, 110 recommended a major construction project, including cases where the benefits and value were low or uncertain. The do-nothing alternative was generally included as a reference but not treated as a viable option. Do-minimum alternatives were often not explored. By contrast, the external QA reports recommended do-nothing or do-minimum in 28 cases. Interestingly, although political decision-makers rarely reject projects, they may put them on hold indefinitely, implying that the actual outcome in many cases is still do-nothing.

Originality/value

The paper addresses a topic that has been understudied in the literature. The findings contribute to the broader literature on project initiation processes, project appraisal and how to reduce the risk of bias and manipulation in appraisals.

Details

International Journal of Managing Projects in Business, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1753-8378

Keywords

Article
Publication date: 28 March 2022

Muhammad Ayat, Azmat Ullah and Changwook Kang

The primary purpose of this study is to explore the relationship between the unsolicited proposal (USP) and the performance of private participation infrastructure (PPI) projects…

Abstract

Purpose

The primary purpose of this study is to explore the relationship between the unsolicited proposal (USP) and the performance of private participation infrastructure (PPI) projects in developing countries.

Design/methodology/approach

The main data set for this study was collected from the World Bank database consisting of 8,951 PPI projects that occurred in developing countries from 1996 to 2020. Hierarchical logistic regression was applied for investigating the effects of USPs on project success. Three moderators, namely, control of corruption, presence of local sponsor and project size were also included in the model to test the impact of their interactions with the USP on the performance of PPI projects. Further, to assess the impact of the effect of USPs, the average marginal effect was calculated. The framework used in this study consists of 18 control variables, three moderators and one noncontrolled independent variable (the USP).

Findings

The results of hierarchical logistic regression indicate that USPs have a significant and negative effect on the success of PPI projects occurring in developing countries. The negative effect of a USP weakens with the presence of local sponsors and stronger control of corruption in the host country. However, contrary to the authors’ expectations, the results show that project size does not significantly affect the association between USPs and the success of PPI projects. Moreover, the results of average marginal effects show that the negative impact of USP on the success of PPI projects ranges between 2.4% and 3.8%.

Originality/value

This study quantifies the negative impact of USP on the success of PPI projects in developing countries, which will be helpful for the practitioners to understand the associated risk with USP projects. Furthermore, it also identifies the moderating roles of control of corruption and the presence of local sponsors on the relationship between USP and the success of PPI projects.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 3
Type: Research Article
ISSN: 1726-0531

Keywords

Open Access
Article
Publication date: 23 April 2024

Anna Kadefors, Kirsi Aaltonen, Stefan Christoffer Gottlieb, Ole Jonny Klakegg, Pertti Lahdenperä, Nils O.E. Olsson, Lilly Rosander and Christian Thuesen

Relational contracting is increasingly being applied to complex and uncertain construction projects. However, it has proved hard to achieve stable performance and industry-level…

Abstract

Purpose

Relational contracting is increasingly being applied to complex and uncertain construction projects. However, it has proved hard to achieve stable performance and industry-level learning in this field. This paper employs an institutional perspective to analyze how legitimacy for relational contracting has been produced and challenged in Denmark, Finland, Norway and Sweden, including implications for dissemination and learning.

Design/methodology/approach

A collaborative case study design is used, where longitudinal accounts of the developments in relational contracting over more than 25 years in four Nordic countries were developed by scholars based in each country. The descriptions are underpinned by literature sources from research, practice and policy.

Findings

The countries share similar problem perceptions that have triggered the de-institutionalization of traditional contracting practices. Models and policies developed elsewhere are important sources of knowledge and legitimacy. Most countries have seen pendulum movements, where dissemination of relational contracting is followed by backlashes when projects fail to meet projected outcomes. Before long, however, relational contracting tends to re-emerge under new labels and in slightly new forms. Such a proliferation of concepts presents further obstacles to learning. Successful institutionalization is found to rely on realistic goals in combination with broad competence development at the organizational and industry levels.

Practical implications

In seeking inspiration from other countries, policymakers should go beyond contract models to also consider strategies to manage industry-level learning.

Originality/value

The paper provides a unique longitudinal cross-country perspective on the field of relational contracting. As such, it contributes to the small stream of literature on long-term institutional change in the construction sector.

Details

International Journal of Managing Projects in Business, vol. 17 no. 8
Type: Research Article
ISSN: 1753-8378

Keywords

Article
Publication date: 20 May 2024

Helene Berg and Ole Henning Nyhus

Value creation for society from public projects requires that the overall benefits exceed the use of taxpayers' money. At the same time, cost overruns in public projects are a…

Abstract

Purpose

Value creation for society from public projects requires that the overall benefits exceed the use of taxpayers' money. At the same time, cost overruns in public projects are a well-documented feature in the literature, but practical guidance on reducing the extent and magnitude of overruns is rare. In 2000, Norway introduced a governance regime that includes mandatory external quality assurance (QA) of cost estimates for major public projects. This paper compares the cost performance of public projects on each side of this QA scheme.

Design/methodology/approach

We use an original dataset covering 1,704 projects from 2000 to 2021, reported first-hand from Norwegian public agencies. We apply quantitative methods in the form of descriptive statistics, regression models, and statistical testing of hypotheses to answer our research questions.

Findings

The mean cost overrun across projects in our dataset is smaller than several previous international studies have reported. We find no statistical support for different cost performances between QA and non-QA projects. Secondly, cost overruns seem to vary between different public sectors. A third finding is a small development with lower cost overruns over time for the non-QA projects, and we raise the question of whether the QA scheme has contributed to overall learning effects. The fourth finding is that cost deviations are quite independent of project size.

Originality/value

The paper offers novel insights for decision-makers and researchers on the effects of external quality assurance on cost performance in public projects.

Details

International Journal of Managing Projects in Business, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1753-8378

Keywords

Article
Publication date: 12 April 2024

Jiajia Cheng, Lianying Zhang, Mingming He and Yingying Yao

Project-based organizations (PBOs) face challenges to enhance employee work engagement because of dynamic and constant role configuration. Accordingly, this study aims to explore…

Abstract

Purpose

Project-based organizations (PBOs) face challenges to enhance employee work engagement because of dynamic and constant role configuration. Accordingly, this study aims to explore how ethical leadership enhances employee work engagement from a sensemaking perspective.

Design/methodology/approach

This study used a questionnaire-based quantitative research design to collect data from 194 full-time employees in PBOs. The data were analyzed via partial least squares-structural equation modeling (PLS-SEM) technique to test hypotheses.

Findings

The findings show a positive relationship between ethical leadership and work engagement. Additionally, the relationship between ethical leadership and work engagement is mediated by two sensemaking mechanisms, i.e. goal commitment and prosocial.

Originality/value

This study deepens the understanding of how ethical leadership enhances work engagement in PBOs by providing two sensemaking mechanisms. By exploring the sensemaking process through which ethical leaders help employees construct identity, the findings contribute to the current literature on how ethical leadership enhances work engagement in PBOs.

Details

Leadership & Organization Development Journal, vol. 45 no. 4
Type: Research Article
ISSN: 0143-7739

Keywords

Open Access
Article
Publication date: 26 May 2023

Sina Moradi and Piia Sormunen

The construction industry has considerably evolved in the recent two decades due to the emergence of sustainability, lean construction (LC) and building information modelling…

3280

Abstract

Purpose

The construction industry has considerably evolved in the recent two decades due to the emergence of sustainability, lean construction (LC) and building information modelling (BIM). Despite previous research efforts, there is still a gap concerning the multidimensional nature of their integration. Hence, this study aims to fill the mentioned knowledge gap through exploring and comparing the challenges, enablers, techniques as well as benefits of integrating LC with BIM and sustainability in building construction projects.

Design/methodology/approach

A systematic literature review was conducted to fulfill the purpose of this study.

Findings

The findings reveal and compare the challenges, enablers, techniques and benefits of integrating LC with BIM and sustainability in building construction projects. The results suggest that there are eight common challenges for integrating LC with BIM and sustainability, including high initial cost, lack of collaboration, lack of professionals and lack of compatible contractual framework. The discovered challenges, enablers, techniques and benefits seem to be mostly routed in people. The findings also suggest that the synergistic benefits of integrating LC with BIM and sustainability can overcome the common challenges (safety, reliability, productivity, collaboration and quality) in construction projects.

Originality/value

The findings contribute to the literature and practice concerning the integration of LC with BIM and sustainability by exploring, comparing and discussing the relevant challenges, enablers, techniques as well as benefits. Moreover, the findings reveal the significance of the development of people in construction industry, besides processes and technology, as people are always subject of activities in construction while processes and technology are always objects.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 7 May 2024

Leda Sivak, Luke Cantley, Rachel Reilly, Janet Kelly, Karen Hawke, Harold Stewart, , Andrea McKivett, Shereen Rankine, Waylon Miller, Kurt Towers and Alex Brown

Aboriginal and Torres Strait Islander (Aboriginal) people are overrepresented in Australian prisons, where they experience complex health needs. A model of care was designed to…

Abstract

Purpose

Aboriginal and Torres Strait Islander (Aboriginal) people are overrepresented in Australian prisons, where they experience complex health needs. A model of care was designed to respond to the broad needs of the Aboriginal prisoner population within the nine adult prisons across South Australia. The purpose of this paper is to describe the methods and findings of the Model of Care for Aboriginal and Torres Strait Islander Prisoner Health and Wellbeing for South Australia.

Design/methodology/approach

The project used a qualitative mixed-method approach, including a rapid review of relevant literature, stakeholder consultations and key stakeholder workshop. The project was overseen by a Stakeholder Reference Group, which met monthly to ensure that the specific needs of project partners, stakeholders and Aboriginal communities were appropriately incorporated into the planning and management of the project and to facilitate access to relevant information and key informants.

Findings

The model of care for Aboriginal prisoner health and wellbeing is designed to be holistic, person-centred and underpinned by the provision of culturally appropriate care. It recognises that Aboriginal prisoners are members of communities both inside and outside of prison. It notes the unique needs of remanded and sentenced prisoners and differing needs by gender.

Social implications

Supporting the health and wellbeing of Indigenous prison populations can improve health outcomes, community health and reduce recidivism.

Originality/value

Only one other model of care for Aboriginal prisoner health exists in Australia, an Aboriginal Community Controlled Health Organisation-initiated in-reach model of care in one prison in one jurisdiction. The South Australian model of care presents principles that are applicable across all jurisdictions and provides a framework that could be adapted to support Indigenous peoples in diverse prison settings.

Details

International Journal of Prison Health, vol. 20 no. 2
Type: Research Article
ISSN: 2977-0254

Keywords

Article
Publication date: 10 March 2022

Huimin Li, Chenchen Xu, Yongchao Cao and Chengyi Zhang

The purpose of this paper is twofold: first, it explores the influencing factors of the government’s trust decision-making in the private sector; second, it explores how these…

Abstract

Purpose

The purpose of this paper is twofold: first, it explores the influencing factors of the government’s trust decision-making in the private sector; second, it explores how these influencing factors affect the government’s trust decisions.

Design/methodology/approach

A theoretical model was established, and a questionnaire survey was conducted among 152 professionals. The collected datas were analyzed by the structural equation modeling (SEM) method.

Findings

The study identified four critical factors that influence the government’s decision to trust the private sector in public-private-partnership (PPP) projects. All the four factors have a positively correlated impact on the government’s trust decision-making. The structural equation path analysis shows that the most important factor affecting the government’s trust decision-making is the trustee’s (private sector) trustworthy characteristics, and the path coefficient is 0.92. The path coefficients of risk perception and the trustor’s trust tendency are 0.83 and 0.74, respectively. The influence of the legal system environment on government trust decision-making is moderate, with a path coefficient of 0.68.

Originality/value

This paper contributes to the literature in two aspects. First, the factors influencing decision-making to government trust in the private sector in PPP projects have been identified. Second, a comprehensive view of the mechanism of government trust in the private sector in PPP projects has been theorized by the SEM method.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 3
Type: Research Article
ISSN: 1726-0531

Keywords

1 – 10 of over 1000